空壓機的停(tíng)用在各個(gè)單位(wèi)都常有發(fā)生。那(nà)麼(me)在初次開機前(qián)空壓機(jī)停放時(shí)間(jiān)超過(guò)三個月或空壓(yā)機停用時(shí)間超(chāo)過三個月,再次開機前需(xū)要采取有效(xiào)措施,bi須(xū)先請(qǐng)專業空壓機(jī)人員對機器(qì)進行保養檢(jiǎn)測,制定(dìng)安全措施(shī),避免開機(jī)後發(fā)生不(bú)良狀(zhuàng)況。

the shutdown of air compressors often occurs in various units. then, before the first start-up, the air compressor parking time is more than three months or the air compressor parking time is more than three months. before the second start-up, effective measures need to be taken. the bi must first ask professional air compressor personnel to carry out maintenance and inspection of the machine, and formulate safety measures to avoid adverse conditions after the start-up.



1、先檢查電路(lù)狀态(tài),是否正常供電(diàn),電壓是(shì)否(fǒu)穩定(dìng);測量(liàng)電動機絕(jué)緣電阻(zǔ),數(shù)值大(dà)于(yú)1mΩ。

1. check the state of the circuit first, whether the power supply is normal, whether the voltage is stable; measure the insulation resistance of the motor, the value is greater than 1m.



2、檢(jiǎn)查空壓機(jī)配件上是否含(hán)有積水,灰塵,及(jí)時清理。

2. check whether there is water and dust on the spare parts of air compressor, and clean them up in time.



3、對進氣口,出(chū)氣口全面(miàn)檢測,防止(zhǐ)發生(shēng)堵塞(sāi)現象(xiàng)

3. overall inspection of intake and outlet to prevent blockage



4、在上(shàng)述都(dōu)已經(jīng)完成(chéng)的情(qíng)況可(kě)以接(jiē)通電(diàn)源(yuán),查(chá)看電腦控制(zhì)器是否(fǒu)正常運行

4. if all the above have been completed, the power supply can be connected to check whether the computer controller is working properly.



5、更換三濾(lǜ)和潤滑油。因為在長期不(bú)用的(de)情況下,三(sān)濾,油可能發生(shēng)老化現象(xiàng),從而(ér)造成空壓機開(kāi)機運(yùn)行時間不(bú)長即結(jié)膠積碳或堵塞,油(yóu)路不(bú)暢使空壓機主(zhǔ)機或(huò)其他零部(bù)件損壞(huài)。

5. replace three filters and lubricants. because in the case of long-term non-use, three filters may cause oil aging phenomenon, which causes the air compressor start-up time is not long, that is, cementing carbon deposit or blockage, oil circuit is not smooth, so that air compressor main engine or other parts are damaged.



6、專(zhuān)業人(rén)員試機,電路改(gǎi)造後人工控制(zhì)加載(zǎi)卸載(zǎi),先空(kōng)載運行10分(fèn)鐘以(yǐ)上,檢測(cè)各項指(zhǐ)标和震動、噪音(yīn)等正常(cháng),再進行(háng)加載,查(chá)看(kàn)各(gè)部(bù)件運(yùn)行正常即(jí)可。

6. professional personnel test machine, after circuit modification, manual control loading and unloading, first no-load operation for more than 10 minutes, detection of various indicators and vibration, noise and other normal, then load, check the normal operation of the components.